Two impressive results for INTECO at Ruspolymet: First Heat and FAC

First Heat with the new ESR

In April 2015 INTECO was able to reach two important milestones at its Russian prime customer Ruspolymet.

Beginning of this month the first heat was successfully carried out at the INTECO ESR plant. This 10t combined short collar- and static mold plant can produce ingots with a diameter of 750 mm and uses electrodes from the INTECO VIM plant.

The Final Acceptance Certificate (FAC) for the complete engineering, supply and installation of a 3t multi-chamber vacuum induction melting furnace has been signed and therefore this first order from Ruspolymet successfully completed.

The further commissioning of the ESR furnace is scheduled until end of May 2015.