Inteco

First Heat at Deutsche Edelstahlwerke Witten

In January 2014 the first heat at the new secondary metallurgical centre at Deutsche Edelstahlwerke Witten was carried out. The melting process on the new treatment line’s ladle furnace and VD/VOD plant was realized without any major difficulties and delays.

This was the first important milestone of the start up phase, which took place according to schedule.

The first part of this large scale project comprised the revamping of the existing secondary metallurgical line and was finalized mid of 2012.